Question 1
A spill containment program must be able to contain:
- One gallon at a time
- The entire volume being transferred
- Only what the supervisor estimates
- Half of the volume
Show the answer
B. The entire volume being transferred — 1910.120(j)(1)(viii) requires containing and isolating the entire volume being transferred.
Question 2
Which item must the site safety and health plan address about monitoring?
- Where to buy meters cheaply
- The colour of monitoring equipment
- Who may borrow the meters
- Frequency and types of air monitoring
Show the answer
D. Frequency and types of air monitoring — 1910.120(b)(4)(ii)(E) covers frequency and types of air monitoring and calibration of equipment.
Question 3
According to Appendix C, who is a good example of a professional to run the safety program?
- The client's receptionist
- Any new laborer
- A Certified Safety Professional
- The company's sales manager
Show the answer
C. A Certified Safety Professional — Appendix C cites Certified Safety Professionals, Board Certified Industrial Hygienists or Registered Professional Safety Engineers.
Question 4
Excavations created during site work must be:
- Filled with water to keep the dust down
- Left open, with a warning sign only
- Shored or sloped per 29 CFR 1926 subpart P
- Covered only with plastic sheeting
Show the answer
C. Shored or sloped per 29 CFR 1926 subpart P — 1910.120(b)(1)(iii) requires shoring or sloping per subpart P of part 1926.
Question 5
Which is a required part of the written safety and health program?
- A marketing plan for future cleanup bids
- A profit forecast for the project
- A list of past clients and references
- A site-specific safety and health plan
Show the answer