Question 1

Which items must be deducted from the chart capacity?

  1. The operator's weight
  2. Hook block, slings, spreader bars, and stowed or erected jibs as specified
  3. Fuel
  4. The cab
Show the answer

B. Hook block, slings, spreader bars, and stowed or erected jibs as specified — Check the chart's notes.

Question 2

Why do load charts specify the quadrant of operation?

  1. For appearance
  2. For travel routes
  3. To set swing speed
  4. Capacity varies depending on whether the load is over the front, side or rear
Show the answer

D. Capacity varies depending on whether the load is over the front, side or rear — Some cranes have reduced capacity over the front.

Question 3

What should an operator do if the load weight is unknown?

  1. Ask the rigger to estimate it quickly by eye and then lift
  2. Use the LMI to guess
  3. Lift it slowly to see
  4. Determine the weight before lifting
Show the answer

D. Determine the weight before lifting — Use drawings, scales or calculations.

Question 4

Under ASME B30.5, for a crawler crane, rated loads are no more than what percentage of the tipping load?

  1. 50%
  2. 75%
  3. 85%
  4. 90%
Show the answer

B. 75% — This provides a stability margin.

Question 5

What must be done if the crane isn't level?

  1. Raise the boom higher
  2. Lift anyway
  3. Reduce the load by 5% only
  4. Level it as required by the manufacturer (often within 1%) before lifting
Show the answer

D. Level it as required by the manufacturer (often within 1%) before lifting — Out-of-level cranes lose capacity quickly.