Question 1
What must follow a leak repair on a covered chiller?
- Nothing
- A new refrigerant type
- Initial and follow-up verification tests
- Removal and replacement of the rupture disc
Show the answer
C. Initial and follow-up verification tests — Verification tests confirm that the repair has stopped the leak.
Question 2
A comfort-cooling chiller with 50 lb or more of ODS refrigerant leaks more than what annual percentage before repair is required?
- 10%
- 20%
- 30%
- 35%
Show the answer
A. 10% — Industrial process chillers have a 30% threshold.
Question 3
What record should be kept of purge unit operation?
- The chiller's paint colour
- Purge run time or counts, which help track leaks
- Nothing
- The colour and smell of the purge unit's exhaust gases
Show the answer
B. Purge run time or counts, which help track leaks — Increasing purge operation indicates a leak.