NASCLA Commercial General Building Contractor — Practice Exam
Procurement and contracting: project administration: practice questions
Our NASCLA Commercial GC bank has 10 questions on this topic. Here are 5 of them with answers; the full mock exam draws from every topic, like the real one.
Question 1
What is value engineering?
- Reducing quality to save money
- Increasing the contract price
- Reviewing the design to cut cost while keeping required function
- Valuing the property for property tax purposes after completion of the building
Show the answer
C. Reviewing the design to cut cost while keeping required function — Savings may be shared under some contracts.
Question 2
What is 'float ownership' in a schedule dispute?
- The ownership of equipment used on the job
- The ownership of the building
- The ownership of materials stored off site
- The question of which party may use schedule slack
Show the answer
D. The question of which party may use schedule slack — Contracts often say float belongs to the project.
Question 3
What is the purpose of a pre-construction meeting?
- To negotiate the contract price with the low bidder before award of the contract
- To review roles, procedures, schedule, safety and submittals before work starts
- To open bids
- To accept the project
Show the answer
B. To review roles, procedures, schedule, safety and submittals before work starts — Minutes should be distributed to all parties.
Question 4
What is a notice to proceed?
- A stop-work order
- A final inspection notice
- The building permit
- A written notice from the owner authorizing the start of work
Show the answer
D. A written notice from the owner authorizing the start of work — Contract time often starts on its date.
Question 5
Why should daily logs be kept on a project?
- They record work, weather, crews, visitors and problems, supporting claims and disputes
- They are only for the owner's use
- They are required to get paid in every state
- They replace the schedule
Show the answer
A. They record work, weather, crews, visitors and problems, supporting claims and disputes — Contemporaneous records are strong evidence.
More NASCLA Commercial GC topics
- General requirements: safety
- Site construction: excavation
- Site construction: stormwater
- Site construction: earthwork
- Concrete
- Masonry
- Metals
- Wood
- Doors, windows and glazing
- Mechanical and plumbing
- Electrical
- Procurement and contracting: payroll taxes
- Procurement and contracting: contracts
- Procurement and contracting: insurance
- Procurement and contracting: business organization