NASCLA Commercial General Building Contractor — Practice Exam
Site construction: earthwork: practice questions
Our NASCLA Commercial GC bank has 12 questions on this topic. Here are 4 of them with answers; the full mock exam draws from every topic, like the real one.
Question 1
A rod reading on a benchmark of elevation 100.00 ft is 4.50 ft, and the reading on a point is 6.25 ft. What is the point's elevation?
- 98.25 ft
- 101.75 ft
- 104.50 ft
- 110.75 ft
Show the answer
A. 98.25 ft — Height of instrument 104.50 − 6.25 = 98.25.
Question 2
100 bank cubic yards of soil has a 25% swell. How many loose cubic yards must be hauled?
- 75 loose cubic yards
- 100 loose cubic yards
- 125 loose cubic yards
- 250 loose cubic yards
Show the answer
C. 125 loose cubic yards — 100 × 1.25.
Question 3
What is a benchmark in site surveying?
- The center of the building
- A fixed point of known elevation
- The property's corner pin set by the surveyor
- A temporary fence post
Show the answer
B. A fixed point of known elevation — Elevations on site are carried from it.
Question 4
What is 'swell' in earthwork?
- The increase in soil volume when it is excavated and loosened
- The height of a fill above grade
- Water absorbed by clay after rain
- The decrease in soil volume when it is compacted in thin lifts
Show the answer
A. The increase in soil volume when it is excavated and loosened — Loose volume = bank volume × (1 + swell).
More NASCLA Commercial GC topics
- General requirements: safety
- Site construction: excavation
- Site construction: stormwater
- Concrete
- Masonry
- Metals
- Wood
- Doors, windows and glazing
- Mechanical and plumbing
- Electrical
- Procurement and contracting: payroll taxes
- Procurement and contracting: contracts
- Procurement and contracting: insurance
- Procurement and contracting: business organization
- Procurement and contracting: project administration