NASCLA Commercial General Building Contractor — Practice Exam
Site construction: stormwater: practice questions
Our NASCLA Commercial GC bank has 9 questions on this topic. Here are 3 of them with answers; the full mock exam draws from every topic, like the real one.
Question 1
Where should concrete washout water go?
- Into a nearby creek
- Into a designated, lined washout area, never into storm drains
- Onto bare soil anywhere on site
- Into the nearest storm drain, after the solids have settled out for a day
Show the answer
B. Into a designated, lined washout area, never into storm drains — Washout water is highly alkaline.
Question 2
Under the 14-day inspection option in EPA's https://www.epa.gov/system/files/documents/2025-04/2022-cgp-permit-as-modified.pdf, what storm triggers an extra inspection within 24 hours?
- 0.25 inches of rain or more in 24 hours
- Any rain at all during working hours, however light
- 2 inches of rain in 24 hours, or a declared flood
- Only a declared flood
Show the answer
A. 0.25 inches of rain or more in 24 hours — Snowmelt from 3.25 inches of snow also counts.
Question 3
What is the purpose of silt fence on a construction site?
- To keep the public off the site and mark the property lines at the same time
- To stop concentrated flow from large drainage areas
- To trap sediment from sheet flow before it leaves the site
- To mark property lines
Show the answer
C. To trap sediment from sheet flow before it leaves the site — It isn't meant for concentrated flow in channels.
More NASCLA Commercial GC topics
- General requirements: safety
- Site construction: excavation
- Site construction: earthwork
- Concrete
- Masonry
- Metals
- Wood
- Doors, windows and glazing
- Mechanical and plumbing
- Electrical
- Procurement and contracting: payroll taxes
- Procurement and contracting: contracts
- Procurement and contracting: insurance
- Procurement and contracting: business organization
- Procurement and contracting: project administration