Question 1 · Wastewater Collection Class I
Before working on a lift station pump, what must be done?
- Turn it off at the panel only and start work
- Ask someone to watch the switch
- Lock out and tag out power and isolate the pump from the wet well and force main
- Turn it off at the control panel only and start work while a coworker watches the switch
Show the answer
C. Lock out and tag out power and isolate the pump from the wet well and force main — 29 CFR 1910.147.
Question 2 · Wastewater Collection Class I
Why is forced-air ventilation used before and during manhole entry?
- To cool the wastewater and dry the pipe walls
- To dry the pipe
- To push odors into nearby homes
- To dilute and remove hazardous gases and supply fresh air
Show the answer
D. To dilute and remove hazardous gases and supply fresh air — Continue testing during entry.
Question 3 · Wastewater Collection Class I
What PPE is important when operating a high-pressure jetter?
- Eye and face protection, gloves and hearing protection
- Only a hat and boots, since water pressure is low
- No PPE
- A respirator only
Show the answer
A. Eye and face protection, gloves and hearing protection — High-pressure water can cause serious injury.
Question 4 · Wastewater Collection Class I
How deep can a trench be before OSHA generally requires a protective system?
- 2 feet
- 5 feet
- 10 feet
- 20 feet
Show the answer
B. 5 feet — Unless in stable rock; 1926.652.
Question 5 · Wastewater Collection Class I
Which gas in sewers smells like rotten eggs and can be deadly?
- Nitrogen
- Carbon dioxide
- Methane produced by decomposing sludge in the sewer
- Hydrogen sulfide
Show the answer
D. Hydrogen sulfide — It deadens the sense of smell at high levels.
More Water/Wastewater Operator topics
- WT treatment: coagulation
- WT treatment: filtration
- WT treatment: disinfection
- WT treatment: operation
- WT math
- WT lab
- WT equipment
- WT source water
- WT safety
- WT admin
- WW secondary: activated sludge
- WW secondary: fixed film
- WW solids
- WW effluent
- WW equipment: aeration
- WW equipment: pumps
- WW equipment: instruments
- WW lab
- WW safety
- WW process
- WD components: mains
- WD components: valves
- WD components: hydrants
- WD components: storage
- WD components: meters
- WD equipment: installation
- WD equipment: repair
- WD equipment: maintenance
- WD quality
- WD admin
- WC system
- WC O&M
- WC lift stations
- WC monitoring