Question 1 · Water Distribution Class I
Why is new pipe kept capped and clean during installation?
- Capping the pipe keeps it warm so the gaskets seal faster after installation
- To speed up the job
- Dirt, animals and trench water can contaminate the main
- To keep the pipe warm so joints seal faster
Show the answer
C. Dirt, animals and trench water can contaminate the main — Contamination makes disinfection harder.
Question 2 · Water Distribution Class I
What is a service tap?
- A storage tank outlet
- A hydrant valve used for flushing at the end of a main
- A connection drilled into a main to supply a customer service line
- A hydrant valve installed at the end of a main for flushing and fire flow testing
Show the answer
C. A connection drilled into a main to supply a customer service line — Wet taps are done under pressure.
Question 3 · Water Distribution Class I
Why are new mains pressure tested before backfilling joints, where practical?
- To measure flow
- To clean the pipe and raise the water quality before backfilling
- To find leaks while joints are still exposed
- To raise water quality
Show the answer
C. To find leaks while joints are still exposed — Pressure and leakage testing per AWWA.
Question 4 · Water Distribution Class I
What bedding is generally placed under water pipe in a trench?
- Large boulders spaced along the trench to support each joint
- Uniform, compacted bedding free of large rocks
- Nothing; pipe lies on any soil
- Large boulders for support
Show the answer
B. Uniform, compacted bedding free of large rocks — Ten States Standards 8.7.2.
Question 5 · Water Distribution Class I
What common chlorine dose is used to disinfect new mains by the continuous-feed method?
- About 500 mg/L for 1 minute
- About 0.2 mg/L for 1 hour, the same as normal distribution residual
- About 25 mg/L, with a residual of at least 10 mg/L after 24 hours
- About 4 mg/L for 5 minutes
Show the answer
C. About 25 mg/L, with a residual of at least 10 mg/L after 24 hours — AWWA C651 continuous-feed method.
More Water/Wastewater Operator topics
- WT treatment: coagulation
- WT treatment: filtration
- WT treatment: disinfection
- WT treatment: operation
- WT math
- WT lab
- WT equipment
- WT source water
- WT safety
- WT admin
- WW secondary: activated sludge
- WW secondary: fixed film
- WW solids
- WW effluent
- WW equipment: aeration
- WW equipment: pumps
- WW equipment: instruments
- WW lab
- WW safety
- WW process
- WD components: mains
- WD components: valves
- WD components: hydrants
- WD components: storage
- WD components: meters
- WD equipment: repair
- WD equipment: maintenance
- WD quality
- WD admin
- WC system
- WC O&M
- WC lift stations
- WC monitoring
- WC safety