Question 1 · Water Distribution Class I
What usually happens to a pipe's C-factor as old unlined cast iron mains age?
- It stays the same
- It stays exactly the same
- It increases as the pipe walls wear smooth from years of flow
- It decreases as tuberculation roughens the pipe
Show the answer
D. It decreases as tuberculation roughens the pipe — Cleaning and lining can restore capacity.
Question 2 · Water Distribution Class I
Before a new main is placed in service, what must be done?
- Paint every hydrant on the new main and fill it with untreated raw water so the joints settle in
- Nothing; it can be used immediately
- Paint the hydrants and fill the main with untreated raw water to settle it
- Pressure and leak test it, disinfect it and get satisfactory bacteriological results
Show the answer
D. Pressure and leak test it, disinfect it and get satisfactory bacteriological results — AWWA standards cover testing and disinfection.
Question 3 · Water Distribution Class I
How deep must water mains be buried in cold climates?
- Only 6 inches
- Exactly 2 feet everywhere
- Below the frost line
- At the surface
Show the answer
C. Below the frost line — Cover depth depends on local frost penetration.
Question 4 · Water Distribution Class I
What does the Hazen-Williams C-factor describe?
- The pipe's pressure rating, in pounds per square inch at the working temperature
- The pipe's chlorine demand
- The smoothness (carrying capacity) of a pipe's interior
- The chlorine demand in the pipe
Show the answer
C. The smoothness (carrying capacity) of a pipe's interior — Higher C means smoother pipe and less head loss.
More Water/Wastewater Operator topics
- WT treatment: coagulation
- WT treatment: filtration
- WT treatment: disinfection
- WT treatment: operation
- WT math
- WT lab
- WT equipment
- WT source water
- WT safety
- WT admin
- WW secondary: activated sludge
- WW secondary: fixed film
- WW solids
- WW effluent
- WW equipment: aeration
- WW equipment: pumps
- WW equipment: instruments
- WW lab
- WW safety
- WW process
- WD components: valves
- WD components: hydrants
- WD components: storage
- WD components: meters
- WD equipment: installation
- WD equipment: repair
- WD equipment: maintenance
- WD quality
- WD admin
- WC system
- WC O&M
- WC lift stations
- WC monitoring
- WC safety